Percentage-of-Completion
20
1999: Calculations:
(a) Estimated gross profit: (note: total gross profit has changed!)
$4.5 million - $4.05 million = $ .45 million estimated profit end 1999
(b) Percent complete so far:
$2,916,000 = 72%
$4,050,000